Section two of the Rodgers Centre stadium renovation noticed the infield and associated seating demolished and rebuilt in months.
Photograph courtesy Toronto Blue Jays
Rogers Centre Renovation Section 2
Toronto, Ontario
Finest Challenge
Submitted by: PCL Constructors Canada Inc.
Proprietor: Toronto Blue Jays
Development Supervisor: PCL Constructors Canada Inc.
Structural Engineer: Entuitive
MEP Engineer: Crossey Engineering
Guide: RISE DBI
Consumer Consultant: Legends Challenge Improvement
The renovation of the house of Main League Baseball’s Toronto Blue Jays had a agency six months to complete, with no further innings. The primary section of the Rodgers Centre improve had up to date the ballpark’s outfield and outer seating areas, however section two tackled the infield and close to seating—an effort practically double in mission scope.
Demolition and renovation schedules left little room for error, however upfront planning ensured that a number of crews labored round one another with out delays. The whole infield was demolished together with adjoining seating, locker rooms and the gamers’ clubhouse.
Photograph courtesy Toronto Blue Jays
Crews labored 24/7 in the course of the first two months of the schedule, and structural demolition of the decrease bowl of the infield was accomplished in solely 13 days. All demolition, excavation and basis work completed in simply 49 days. Work on the mission started in October 2023 and was full by Might 2024, earlier than the beginning of the Blue Jays’ season this yr.
In depth use of 3D mapping let the crew make certain the sphere was as much as league requirements whereas proactive planning of kit staging ensured {that a} forest of cranes and a swarm of excavators and dump vans had most utilization. Two cranes had been used for metal and two for precast concrete, working in live performance to carry out effectively over 600 lifts in the course of the course of the mission.
Photograph courtesy Toronto Blue Jays
To take care of entry to the work space throughout demolition and crane lifts, the crew constructed a brief Bailey Bridge from the loading dock to the infield bowl, permitting dump vans direct entry to take away spill. Demolition work additionally included full elimination of the stadium’s previous monitor system that had allowed for the seating stands to separate and rotate to accommodate different sporting occasions equivalent to video games for the Canadian Soccer League.
The renovation is greater than a refresh for the stadium—bringing not solely improved seating and sightlines for spectators, but additionally a brand new clubhouse in addition to up to date locker rooms and associated amenities.
Jeff Rubenstone is Deputy Editor for Information and Know-how on the Engineering Information-File. As information director of ENR he oversees the publication’s information protection, and in addition covers rising applied sciences and improvements within the building area. With effectively over a decade of expertise reporting on the business, Jeff has a broad background in engineering and building journalism. He’s based mostly in New York Metropolis.